1. Topo contour survey by DGPS and preparation of survey drawing showing spot heights @ 5m, Boundary property limit, existing constructions, existing overhead lines, water body etc.
2. Site visit and data collection.
3. Geotechnical investigation report of the substation plot and submission of soil investigation report.
4. Soil resistivity test at site and submission of soil resistivity test report.
5. Electrical Design and drawings with BOQ.
6. Civil and steel structural design and drawings with BOQ.
7. Design and drawings of Fire protection system with BOQ.
8. Design and drawings of AC and Ventilation system with BOQ.
9. Substation automation system design, drawings, BOQ.
10. Fiber optic communication system / teleprotection system design, drawings and BOQ.
11. Bid evaluation and recommendation.
12. Vendor drawing review and approval.